Drains and sewers: Madipakkam's longest wait

Flooding and sewage are Madipakkam's oldest complaints. Large sums are being spent, but the works have been slow and poorly joined up.

City storm drains (Feb 2026)
About 1,215 of 1,398 km done
Kovalam basin (KfW)
62 of 124 km done, Feb 2026
Madipakkam sewerage
Planned since about 2011; still in progress in 2024
Who to ask
GCC (drains), Metrowater (sewers)

Two systems, two offices

Storm drains carry rainwater and belong to the Corporation. Sewers carry waste water from homes and belong to Metrowater. When either fails, streets flood or sewage reaches the lake. Many Madipakkam problems come from the two being dug at different times.

Storm drains

In February 2026 the Corporation said it had spent Rs 6,475 crore since 2022 on 1,398 km of storm drains across the city, with about 1,215 km done and the rest due by July. The Kovalam basin project, which covers Madipakkam and is funded by the German development bank KfW, is in three phases. Officials said 62 of its 124 km were done.

In 2021 a ward 188 desilting contract was not finished, and the Corporation later admitted in an RTI reply that this helped cause the November floods.

Sewers

Madipakkam's underground sewerage scheme was started around 2011. In July 2019, after a Madipakkam advocate reminded the Madras High Court that the plan had stalled for years, Metrowater said building would start by July 2020 and take three years. In 2024 the ward 188 councillor said large sewer works were still going on in Madipakkam and Ram Nagar, and that drain workers had cut newly laid water pipes, so Metrowater had to redo connections.

Common problems

Roads are dug again and again for drains, sewers, water and cables. Streets are left out of drawings: in 2022, Srinivasa Nagar streets such as Vivekananda, Kavimani and Balaji Streets were missing from the Kovalam drain tender drawings, which officials blamed on an old map. Some new drains elsewhere in the city have turned into stagnant pools because they were not linked properly. In ward 188, an activist alleged in 2022 that contractors' bills were cleared without completion certificates.

Good practice

Ask for one digging plan per street, agreed between the Corporation, Metrowater and the electricity board, before any road is relaid. Ask the zonal office for the drain drawings for your street, and check that the water has somewhere to go. After work is finished, walk it with neighbours and report gaps with photos. Citizen flood audits, like the one done near Medavakkam after Cyclone Michaung, show which links are missing.

Sources

  • DT Next: 88% of SWD works finished, claims GCC; denizens flag inconsistencies, 2026-02-23 (dtnext.in)
  • DT Next: Incomplete drain desilting led to Madipakkam flooding, admits GCC, 2022-02-08 (dtnext.in)
  • News Today: Construction of Madipakkam underground sewage network to begin, 2019-07-22 (newstodaynet.com)
  • Citizen Matters: Councillor Talk, Ward 188 (Sameena Selvam), 2024-07-05 (citizenmatters.in)
  • Citizen Matters: Water supply, sewage issues in Ullagaram-Puzhuthivakkam can be solved only with citizen consultation, 2022-05-05 (citizenmatters.in)
  • Citizen Matters: Citizen flood audit after Medavakkam lake breach, 2024-01-16 (citizenmatters.in)

Written for Namma Madipakkam in our own words, 26 Nov 2026. Rules and amounts change: check with the office named above before you rely on them. Spotted a mistake? Tell us.