Skip to content
Madipakkam stamp emblem மடிப்பாக்கம் Namma Madipakkam
📞Phone numbersஅவசர எண்கள்
← All water supply news
Water supply17 Jan 2018First reported by Deccan Chronicle

Madipakkam to get desalinated sea water from Nemmeli under Rs 67.5 crore AMRUT plan

In January 2018, Metrowater told residents' groups that water-starved Madipakkam would get drinking water made from sea water at the Nemmeli desalination plant. The Rs 67.5 crore project under the AMRUT scheme included a big overhead tank and an underground sump.

Scheme
AMRUT (central urban infrastructure mission)
Agency
Chennai Metrowater (CMWSSB)
Cost
Rs 67.5 crore (33% from the Centre, rest from the State)
Source
Nemmeli desalination plant
Storage
50 lakh-litre overhead tank and 9 lakh-litre underground tank, near Velachery Main Road and Kaiveli
Target
Supply to begin by 2019

What happened

Deccan Chronicle reported on 17 January 2018 that Madipakkam would soon get desalinated water. Desalination is the process of removing salt from sea water so that it is safe to drink. The water would come from Metrowater's plant at Nemmeli, which the paper said supplied 200 million litres a day to the city.

The project, under the central government's AMRUT scheme, would cost Rs 67.5 crore. The Centre would pay a third and the State the rest. Two storage tanks were planned on Corporation land near Velachery Main Road and Kaiveli: an overhead tank holding 50 lakh litres and an underground tank holding 9 lakh litres. Building was to start that year, and supply was expected to begin by 2019. Ullagaram, Puzhuthivakkam and Medavakkam, where pipes had recently been laid, would also benefit.

Why it matters for Madipakkam

For more than a decade, Madipakkam residents had been paying water charges but buying drinking water in cans. Earlier water schemes had failed them because of poor management and broken pipelines. Many houses had pipe connections that never brought any water, and complaints went unanswered.

Residents welcomed the plan, but one resident said the department had to deal seriously with the old pipeline problems so they would not happen again.

Background

Madipakkam has long depended on borewells, street tanks and bought water. In the dry summer of 2019, residents reported borewells going dry near the lake, and some streets padlocked their Metrowater street tanks to stop water being taken at night.

What happened later

The work took longer than planned. In July 2024, Citizen Matters reported that piped water connections had been completed in some parts of ward 188, including Ram Nagar, but that water had not yet reached households. It also said that drain construction had damaged Metrowater pipes and delayed supply. We could not find an official date for when supply began across Madipakkam.

Timeline

  1. Jan 2018Metrowater briefs residents' groups on the Rs 67.5 crore AMRUT plan.
  2. 2019Target date for supply to begin.
  3. Jul 2024Connections laid in parts of ward 188, but water not yet reaching some homes.

Sources

  • Deccan Chronicle: Madipakkam to get desalinated water, 2018-01-17 (deccanchronicle.com)
  • Citizen Matters: Chennai: Flooding and bad roads a perennial problem in Ward 188, 2024-07-29 (citizenmatters.in)
  • News Today: Madipakkam residents lock up roadside Metro tanks fearing water theft at night, 2019-06-21 (newstodaynet.com)

Written for Namma Madipakkam in our own words from the sources above, 26 Nov 2026. Spotted a mistake? Tell us.