Madipakkam underground drainage scheme opened by the Chief Minister

On 29 May 2025, the Chief Minister opened Rs 571.92 crore of Municipal Administration works by video link. They included underground drainage schemes for Pallikaranai, Mugalivakkam and Madipakkam, together estimated at Rs 188.55 crore.

Scheme
Underground drainage (sewerage) schemes: Pallikaranai, Mugalivakkam, Madipakkam
Combined cost
Rs 188.55 crore (no separate figure for Madipakkam)
Opened
29 May 2025, by video link from the Secretariat
Department
Municipal Administration and Water Supply (MAWS)
Total works opened
Rs 571.92 crore, 49 works

What happened

On Thursday, 29 May 2025, Chief Minister M K Stalin opened a set of finished projects of the Municipal Administration and Water Supply (MAWS) department. He did this by video link from the Secretariat in Chennai. DT Next reported that 49 completed works worth Rs 571.92 crore were opened, and foundation stones were laid for 16 new projects.

Among the completed works were underground drainage schemes for Pallikaranai, Mugalivakkam and Madipakkam. Together they were estimated at Rs 188.55 crore. The report did not give a separate cost for Madipakkam, or say how many homes are covered.

Why it matters for Madipakkam

Underground drainage means a network of closed sewer pipes under the streets. It carries waste water from toilets and kitchens to a treatment plant. Without it, homes depend on septic tanks, and dirty water can end up in open drains and lakes.

For Madipakkam this has been a long wait. A 2025 Citizen Matters report said sewage still flows into Madipakkam lake because many nearby areas have no underground drainage. Residents had asked the government for sewage treatment plants.

The work also caused a lot of digging. In May 2025, DT Next reported streets in Karthikeyapuram and Mahalakshmi Nagar that had stayed dug up or unpaved for years, as water, electricity and sewer works followed one after another.

Background

The scheme took many years to reach this point. In July 2019, News Today reported that Metrowater (the Chennai Metropolitan Water Supply and Sewerage Board) was getting a detailed project report ready for water supply and sewerage schemes in 42 newly added areas, including Madipakkam. The project had been stuck for a long time. It moved after a Madipakkam resident took the matter to the Madras High Court. At that time, construction was expected to start by July 2020 and take three years.

What happens next

With the scheme declared complete, households can apply to Metrowater for a sewer connection. Applications are made online at wsc.chennaimetrowater.in. We could not confirm from the sources which streets are fully connected.

Timeline

  1. Jul 2019Project report being prepared; work expected to start by July 2020
  2. May 2025Streets in Madipakkam still dug up for water, power and sewer works
  3. 29 May 2025Chief Minister opens the Pallikaranai, Mugalivakkam and Madipakkam schemes

Sources

  • DT Next: CM Stalin inaugurates Rs 571.92 crore works of MAWS dept, 2025-05-30 (dtnext.in)
  • News Today: Construction of Madipakkam underground sewage network to begin, 2019-07-22 (newstodaynet.com)
  • DT Next: Potholes splinter Madipakkam, residents demand solution, 2025-05-23 (dtnext.in)
  • Citizen Matters: From neglect to nurture: How a proactive community revived Chennai's Madipakkam Lake, 2025-09-24 (citizenmatters.in)
  • DT Next: Chennai: Metro Water reiterates online-only process for new connections, 2026-09-18 (dtnext.in)

Written for Namma Madipakkam in our own words from the sources above, 26 Nov 2026. Spotted a mistake? Tell us.