Velachery-St Thomas Mount MRTS trains finally run after 17 years
வேளச்சேரி - பரங்கிமலை மேம்பால ரயில் சேவை துவக்கம்! 17 ஆண்டு தவிப்பு தீர்ந்தது
The first MRTS train on the new Velachery-St Thomas Mount link ran on 14 March 2026. Trains stop at Puzhuthivakkam, giving Madipakkam, Keelkattalai and Puzhuthivakkam their first direct rail link. Some station facilities were not yet working.
- Line
- MRTS extension, Velachery to St Thomas Mount (Parangimalai)
- Length
- About 5 km (Dinamalar); 4.5 km (DT Next)
- Cost
- Rs 495 crore estimate, rose to Rs 734 crore
- Work began
- 2008
- Opened
- 14 Mar 2026
- New stations
- Puzhuthivakkam (open); Adambakkam (not yet stopping)
What happened
The first train on the Velachery-St Thomas Mount stretch left St Thomas Mount (Parangimalai) at 5 am on 14 March 2026. It went through Velachery and reached Chennai Beach in about an hour. The MRTS is the elevated suburban railway that runs from Chennai Beach to Velachery. That line already carries more than 80 trains a day and over a lakh passengers.
The new link joins the MRTS to St Thomas Mount, where people can change to the Metro and to suburban trains on the Tambaram line. Dinamalar gives its length as 5 km. DT Next gives 4.5 km.
Why it matters for Madipakkam
Until now, Madipakkam, Keelkattalai, Puzhuthivakkam and Adambakkam had no train service close by. Many people rode two-wheelers all the way to Velachery to catch a train. Puzhuthivakkam station is close to Madipakkam. From there residents can now reach Velachery, the Beach and St Thomas Mount directly.
A residents' leader from AGS Colony told Dinamalar that families could save money as they no longer need to ride long distances. She also asked officials to stop street vendors from crowding the station entrances.
Problems at the start
On the first day, the escalators and lifts at Puzhuthivakkam were not working. Drinking water and toilets were not ready, and rubbish had piled up in one part of the station. For older passengers, this means climbing many steps to the platform.
Trains were not stopping at Adambakkam. On 24 March, DT Next reported that a Southern Railway official said the station had not yet been handed over to the operating division. No date was given. Escalators and lifts were being put in at both stations.
Background
Work started in 2008 at an estimated cost of Rs 495 crore. A land dispute at Adambakkam (Thillai Ganga Nagar) held it up for years. The cost rose to Rs 734 crore. Work restarted after 2021 and was completed in November 2025. Freight trains made trial runs on 7 November and 15 December 2025. The Commissioner of Railway Safety then approved the line. The opening was first set for 10 March 2026 but was put off by a few days.
Within ten days of the opening, the number of people using Velachery station had risen from about 35,000 to nearly 70,000 a day.
Timeline
- 2008Construction begins; estimated cost Rs 495 crore
- 2021Work resumes after the Adambakkam land dispute is settled
- Nov 2025Construction completed; first freight trial run on 7 Nov
- 15 Dec 2025Second trial run
- 14 Mar 2026Passenger service begins; trains stop at Puzhuthivakkam
- 24 Mar 2026Adambakkam station still not in use; lifts and escalators being installed