Due by July 2025: the Madipakkam sewer scheme on paper

Report filed by the 7th Respondent (Chennai Metropolitan Water Supply and Sewerage Board), dated 16 April 2025, in Miscellaneous Application No. 07 of 2024 in Original Application No. 55 of 2020 (SZ), National Green Tribunal, Southern Zone

A short April 2025 report to the Green Tribunal gives the most recent official timetable we found for Madipakkam's underground sewerage.

Case
M.A. No. 07 of 2024 in O.A. No. 55 of 2020 (SZ), National Green Tribunal, Southern Zone
Filed by
Superintending Engineer (WWT&R), Metrowater
Date
16 April 2025
Madipakkam row
Estimate Rs 85.20 crore; scheduled completion 31.07.2025
Citywide picture
Of 42 local bodies added to Chennai, sewerage completed in 22; 20 in progress
Why summary only
A report by a government board filed in a tribunal case, not a tribunal order

What this document is

This case began over sewage flowing into Putheri lake in Pallavaram. In its judgment of 18 July 2022 the Tribunal directed the Tambaram and Greater Chennai Corporations to build underground sewerage in uncovered areas 'in a war footing manner'. A later application asked for that to be carried out, and on 20 January 2025 the Tribunal added Metrowater as a party. This report, dated 16 April 2025, is Metrowater's reply.

What it says about Madipakkam

Most of the report is about Pallavaram, which Metrowater says is run by Tambaram Corporation. It notes that Pallavaram's sewage, 8 to 11 million litres a day, is pumped through the Keelkattalai pumping station to the Perungudi treatment plant.

It then lists the 42 local bodies added to the Chennai area. Comprehensive underground sewerage was complete in 22, including neighbouring Ullagaram-Puzhuthivakkam. A table of the 20 still in progress includes Madipakkam, with an estimated cost of Rs 85.20 crore and a scheduled completion date of 31 July 2025. Pallikaranai, the next area to the east, is shown at Rs 39.30 crore and 31 May 2025.

What it means for residents

On paper, the main sewer work for Madipakkam was due to finish by the end of July 2025, after which homes can apply for house service connections. The Rs 85.20 crore figure is lower than the Rs 256.90 crore sanctioned in 2022 and the Rs 205 crore estimate of 2021. The report does not explain the difference; it may refer to a different part of the cost, so treat it with care.

What happened next

Earlier, on 30 November 2023, Metrowater told the Tribunal in another case (O.A. No. 164 of 2014) that 17 of the 42 added areas had sewerage, 15 including Madipakkam were in progress and 10 were at tender stage. We have not found an official document confirming completion of the Madipakkam work or the number of homes connected.

Timeline

  1. 31 Jan 2022Rs 256.90 crore sanctioned for Madipakkam sewerage.
  2. 18 Jul 2022Tribunal judgment in O.A. 55 of 2020 orders sewerage in uncovered areas.
  3. 30 Nov 2023Metrowater lists Madipakkam as 'UGSS under progress'.
  4. 16 Apr 2025Metrowater gives 31 Jul 2025 as Madipakkam's scheduled completion.

Sources

  • National Green Tribunal, reports uploaded in M.A. No. 7 of 2024 (SZ) (greentribunal.gov.in)
  • Report filed by R7 (CMWSSB) in M.A. No. 7 of 2024 in O.A. No. 55 of 2020 (SZ), 2025-04-16 (greentribunal.gov.in)
  • Report filed by CMWSSB in O.A. No. 164 of 2014 (SZ), 30 Nov 2023, 2023-11-30 (greentribunal.gov.in)

Explained for Namma Madipakkam in our own words, 27 Nov 2026. This is not legal advice. Spotted a mistake? Tell us.