Metrowater tells High Court the Madipakkam sewer plan will be ready by August 2019
In a public interest case about Madipakkam's missing sewers, Metrowater told the Madras High Court in July 2019 that its consultant would hand in the final report and draft tender papers by 31 August 2019. It also set out the size and cost of the planned network.
- Court
- Madras High Court (Justices S. Manikumar and Subramonium Prasad)
- Agency
- Chennai Metrowater (CMWSSB)
- Area / people
- 3.40 sq km, 48,710 people
- Network
- 98.84 km of sewers, 6 pumping stations, 8.80 km pumping main, 9,750 house connections
- Outline cost
- Rs 160 crore
- Report deadline
- 31 August 2019
What happened
On 3 July 2019, a two-judge bench of the Madras High Court heard a public interest case filed by P. Ayyamperumal of Madipakkam. He asked the court to make the authorities finish the detailed project report for a Madipakkam underground sewerage scheme and complete the work on a fixed timetable. A detailed project report, or DPR, is the full engineering plan and cost estimate that a project needs before money is sanctioned and tenders are called.
Metrowater's superintending engineer filed a report with the court. It said the consultant, SAI Consulting Engineers, was preparing the final report and a draft tender document and would submit them by 31 August 2019. Metrowater had hired the firm on 24 October 2016, for Rs 1.49 crore, to plan sewers for Madipakkam and 13 other added areas of the city.
What the plan contains
The plan covers an area of 3.40 sq km with a population of 48,710, and is designed to serve for 30 years. It includes about 98.84 km of sewer pipes that work by gravity, and six sewage pumping stations. The report named sites at the dumping yard, Rajalakshmi Nagar, Mylai Balaji Nagar and Senthil Nagar, plus a roadside lift station at Lake View Road and Karpagambal Nagar. An 8.80 km pumping main would carry the sewage to a treatment plant. About 9,750 houses would get connections. The outline cost was Rs 160 crore.
The timetable
After the final report was approved, Metrowater said it would prepare the final tender within 30 days. Then the scheme would get its administrative and technical approval. Choosing a contractor would take up to six months, and building would take 36 months from the award of the contract. The court asked Metrowater to file a further report on the steps it had taken, and listed the case again for 5 July 2019.
Why it matters for Madipakkam
The report put the full size of the planned network, and a set of dates, on the court record. That gave residents something definite to hold the board to.
The work did begin later, but it ran well past the three-year building time. Reports from 2024 described sewer connection work still unfinished in some Madipakkam streets, and roads being dug up again.
Timeline
- 24 Oct 2016Metrowater hires SAI Consulting Engineers for Rs 1.49 crore.
- 3 Jul 2019High Court hears the case; Metrowater files its report.
- 31 Aug 2019Deadline for the final report and draft tender document.
- 2024Sewer connection work still unfinished in parts of Madipakkam.