Skip to content
Madipakkam stamp emblem மடிப்பாக்கம் Namma Madipakkam
📞Phone numbersஅவசர எண்கள்
← All drains & sewage news
Drains & sewage22 Jul 2019First reported by News Today

Metrowater sets July 2020 start for Madipakkam's underground sewers

In July 2019, Chennai Metrowater said work on Madipakkam's underground sewerage system would start by July 2020 and take about three years. The dates were fixed after a resident told the Madras High Court that the scheme had been stuck for years.

Agency
Chennai Metrowater (CMWSSB)
Scheme
Underground sewerage for 42 areas newly added to the city
Planned start
By July 2020
Planned length of work
About 3 years from start
Outline cost
Rs 160 crore (Madipakkam, 2019 estimate)
Consultant
SAI Consulting Engineers

What happened

News Today reported on 22 July 2019 that Chennai Metrowater planned to start building an underground sewerage system in Madipakkam by July 2020. Metrowater's full name is the Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB). It expected the work to be finished within three years of starting.

An underground sewerage system is a network of closed pipes under the streets that carries waste water from homes to a treatment plant. Without it, each house depends on its own septic tank, which can fill up and overflow.

The Madipakkam project was part of a wider scheme to give water supply and sewerage to 42 areas that had been added to the Chennai Corporation. A Metrowater superintending engineer set out the steps: the consultant would hand in the final report and a draft tender document by 31 August 2019, and the final tender was expected to be approved around 31 October 2019.

How the dates were fixed

The timetable came out of a public interest case in the Madras High Court. P. Ayyamperumal, an advocate living in Madipakkam, reminded the court that the plan had been on hold for many years. Metrowater then filed the papers before the court.

In those papers, reported by Deccan Chronicle on 4 July 2019, Metrowater described the design. It would cover 3.40 sq km and about 48,710 people, with about 98.84 km of sewer pipes, six pumping stations, an 8.80 km pumping main and 9,750 house connections. The outline cost was Rs 160 crore.

Why it matters for Madipakkam

Madipakkam joined the Chennai Corporation in 2011 but still had no sewers in 2019. Residents said septic tanks often overflowed onto roads and empty plots, and that this polluted groundwater and spread disease.

What happened later

The work did start, but it took longer than three years. In February 2024, DT Next reported that residents of Karthikeyapuram Second Cross Street were upset because a newly laid road was dug up again for unfinished sewer connection work. The ward 187 councillor, J Shirley Thomas, said most of the Metrowater work was complete. In July 2024, Citizen Matters reported that sewage and drainage works were still going on in Madipakkam and nearby areas.

We could not find an official date when the whole Madipakkam network was finished.

Timeline

  1. 2011Madipakkam is merged into the Chennai Corporation.
  2. 24 Oct 2016Metrowater awards the project report work to SAI Consulting Engineers.
  3. Jul 2019Metrowater tells the High Court its timetable; start set for July 2020.
  4. Feb 2024Residents complain of roads dug up again for unfinished sewer connections.
  5. Jul 2024Sewage and drainage works still under way in Madipakkam.

Sources

  • News Today: Construction of Madipakkam underground sewage network to begin, 2019-07-22 (newstodaynet.com)
  • Deccan Chronicle: Working on final report: CMWSSB, 2019-07-04 (deccanchronicle.com)
  • DT Next: Citizen connect: Re-laid road cut for CMWSSB's incomplete work in Madipakkam, 2024-02-22 (dtnext.in)
  • Citizen Matters: Chennai: Flooding and bad roads a perennial problem in Ward 188, 2024-07-29 (citizenmatters.in)

Written for Namma Madipakkam in our own words from the sources above, 26 Nov 2026. Spotted a mistake? Tell us.