2021 tribunal order: Madipakkam wards 187 and 188 have no sewers at all
In November 2021, the National Green Tribunal, hearing a case on sewage entering Puzhuthivakkam Chitheri lake, recorded that Puzhuthivakkam had sewers but Madipakkam divisions 187 and 188 had no underground drainage at all.
- Court
- National Green Tribunal (NGT), Southern Zone, Chennai
- Case
- O.A. No. 135 of 2020 (SZ), taken up on its own
- Order date
- 15 November 2021
- Lake
- Puzhuthivakkam Chitheri lake
- Finding
- No underground drainage in Madipakkam divisions 187 and 188
What the tribunal said
The National Green Tribunal (NGT) is a special court for environment cases. In July 2020, after a Dinamalar report that sewage was flowing into Puzhuthivakkam Chitheri lake, its Southern Zone bench in Chennai started a case on its own.
In its order of 15 November 2021, according to our summary, the tribunal recorded that Puzhuthivakkam had sewers, while Madipakkam divisions 187 and 188 had no underground drainage at all. It noted that a revised detailed project report (DPR) for a Madipakkam sewerage scheme was being prepared. A DPR is the full engineering plan and cost estimate for a project.
Metrowater's later report shows that the tribunal also asked, in paragraph 5 of this order, for progress on giving sewer connections to homes around the lake.
Why it matters for Madipakkam
In late 2021, ten years after Madipakkam joined the Chennai Corporation, its two wards still had no sewer pipes. Homes used septic tanks, and lorries emptied them. Some waste reached rain drains and lakes, including Chitheri lake, which sits between Puzhuthivakkam and Madipakkam.
What happened next
Metrowater filed progress reports on 24 November 2021 and 4 February 2022, and a further report in March 2022. By then, 824 of 836 homes on the Puzhuthivakkam side had sewer connections. On the Madipakkam side, 109 homes in eight streets still had none.
On 31 January 2022 the government approved Rs 256.90 crore for the Madipakkam sewerage scheme. Metrowater later said the work was awarded on 24 June 2022, began on 1 August 2022 and would include 10,856 house connections. In April 2025 it gave a finish date of 31 July 2025.
A note on sources
We could not open the full text of this order, as the Indian Kanoon page was blocked to us. The order's findings come from our earlier summary. The later steps come from Metrowater's own reports to the tribunal.
Timeline
- 2021State tells the NGT the Madipakkam underground sewerage scheme is estimated at Rs 205 crore.
- 15 Nov 2021NGT records that Madipakkam divisions 187 and 188 have no underground drainage.
- 31 Jan 2022Government order G.O.(Ms) No. 23 gives Rs 256.90 crore approval for Madipakkam sewerage.
- 10 Mar 2022One bid received for the work.
- 24 Jun 2022Contract awarded.
- 1 Aug 2022Work begins.
- Jul 2024Metrowater tells the NGT the work will finish by 31 Jan 2025, with 10,856 house connections.
- Apr 2025Metrowater lists a revised finish date of 31 Jul 2025.