Buses, trains, metro3 May 2022First reported by Maalaimalar

Metro work makes Vanuvampet-Madipakkam road one-way; buses take long detour

மெட்ரோ ரெயில் பணி காரணமாக வாணுவம்பேட்டை-மடிப்பாக்கம் ரோடு ஒரு வழிப்பாதையானது

In May 2022, Metro Phase 2 work turned the Vanuvampet-Madipakkam stretch of the Mount-Medavakkam road one-way. Buses towards Medavakkam were sent round via 200 Feet Road and Kaiveli, and passengers paid Rs 4 extra.

Road
St Thomas Mount (Parangimalai)-Medavakkam Main Road
One-way stretch
Vanuvampet to the Axis Bank point, Madipakkam
Reason
Chennai Metro Rail Phase 2 work
Bus detour
200 Feet Road, Kaiveli, Sadasivam Nagar, Ram Nagar, Palaiah Garden
Extra fare
Rs 4

What happened

On 3 May 2022, the Tamil daily Maalaimalar reported that part of the St Thomas Mount-Medavakkam Main Road had been made one-way because of Chennai Metro Rail Phase 2 work. The stretch ran from Vanuvampet to the Axis Bank point in Madipakkam.

Buses going from St Thomas Mount station through Madipakkam towards Kilkattalai and Medavakkam could no longer use this stretch. Buses coming the other way, from Medavakkam towards St Thomas Mount, were not affected.

The bus detour

From Vanuvampet, the buses now went along the 200 Feet Road. They turned right in front of Velachery railway station and right again at the Kaiveli junction onto the Velachery-Pallikaranai main road. They then passed through Sadasivam Nagar, Ram Nagar and Palaiah Garden to rejoin the main road at the Axis Bank point.

Passengers on these buses had to pay Rs 4 more than the normal fare. Officials said there was no other route.

Why it matters for Madipakkam

People going to Vanuvampet, Oil Mill, Kumaran Theatre and the Madipakkam junction were badly hit. Many took share autos through the inner roads, paying Rs 20 to Rs 30. For elderly people who depend on buses, this meant longer and costlier trips.

Background

The Metro line along this road is Corridor 5 of Phase 2, from Madhavaram to Sholinganallur. In November 2021, a consortium of HCC and KEC International won the contract for the elevated stretch with 11 stations, the first of which is Madipakkam, followed by Kilkattalai and Echangadu.

What happens next

The Maalaimalar report did not say how long the one-way rule would last. In August 2026, DT Next reported that all 513 pillars on the 11.3 km stretch from Ullagaram to Elcot had been cast, and girders and stations were being built.

Sources

  • Maalaimalar: மெட்ரோ ரெயில் பணி காரணமாக வாணுவம்பேட்டை-மடிப்பாக்கம் ரோடு ஒரு வழிப்பாதையானது (Vanuvampet-Madipakkam road made one-way for Metro work), 2022-05-03 (maalaimalar.com)
  • DT Next: CMRL Phase 2: consortium wins Rs 1,309 crore contract, 2021-11-16 (dtnext.in)
  • DT Next: CMRL completes pier work on Corridor 5, 2026-08-26 (dtnext.in)

Written for Namma Madipakkam in our own words from the sources above, 26 Nov 2026. Spotted a mistake? Tell us.