Green tribunal orders action on Madipakkam sewage and lake encroachments
In August 2022, the National Green Tribunal told the Chennai Corporation to stop sewage from parts of Madipakkam reaching the Kovilambakkam surplus channel, and to give Madipakkam underground sewers. It also told the local panchayat union to survey and clear encroachments on three lakes.
- Court
- National Green Tribunal (NGT), Southern Zone, Chennai
- Case
- O.A. No. 40 of 2020 with O.A. No. 93 of 2020 (taken up on its own)
- Order date
- 12 August 2022
- Lakes
- Kilkattalai, Kovilambakkam and Medavakkam
- Deadline
- 3 months to plan, 6 months to carry out the sewage interception
What the tribunal decided
The National Green Tribunal (NGT) is a special court for environment cases. Its Southern Zone bench sits in Chennai. In August 2022 it passed a final order in two cases it had started on its own, after newspaper reports in 2020.
The first report, in The Times of India in February 2020, said sewage was flowing into the surplus channel at Kovilambakkam. A surplus channel carries the extra water out of a lake when it is full. This one carries water from Kilkattalai lake. The second report, in Dinamalar in June 2020, asked when Kovilambakkam lake would be restored.
According to the order's summary on Indian Kanoon, the tribunal directed the Greater Chennai Corporation to catch the sewage flowing from parts of Madipakkam into the Kovilambakkam surplus channel, and send it to the Perungudi sewage treatment plant instead. It gave three months to plan this and six months to do it. It also directed that Madipakkam be given underground sewerage. The St Thomas Mount Panchayat Union was told to survey the Kilkattalai, Kovilambakkam and Medavakkam lakes and remove encroachments.
Why it matters for Madipakkam
Until recently, Madipakkam had no sewer pipes. Each house used a septic tank. Some waste ended up in rain drains, which flow into channels and lakes. This order put a firm deadline on stopping that.
Underground sewerage means closed pipes under the street that carry waste water to a treatment plant.
What happened after
In July 2024, Metrowater filed a report in the same cases. It said a joint team had inspected the surplus channel on 5 August 2022. The Water Resources Department had built retaining walls along the channel. A sewage pipe from Tambaram crosses the channel at Kovilambakkam, and on 30 January 2023 its emergency valve was found closed, with no sewage leaking.
Metrowater said the Madipakkam sewerage project was awarded on 24 June 2022 and work began on 1 August 2022. It said work would finish by 31 January 2025, followed by 10,856 house connections. In an April 2025 report in another case, Metrowater gave a new finish date of 31 July 2025.
Homes still without sewers can book a Metrowater sewer lorry on the 14420 helpline or at stc.chennaimetrowater.in.
A note on sources
We could not open the full text of the August 2022 order, as the Indian Kanoon page was blocked to us. The directions above come from our earlier summary of the order. The later steps come from Metrowater's own reports to the tribunal.
Timeline
- 17 Feb 2020Times of India reports sewage flowing into the Kovilambakkam surplus channel.
- 29 Jun 2020Dinamalar asks when Kovilambakkam lake will be restored. The NGT takes up both reports on its own.
- 1 Aug 2022Madipakkam sewerage work begins.
- 5 Aug 2022Joint team inspects the surplus channel.
- 12 Aug 2022NGT passes its final order.
- 30 Jan 2023Inspection finds the sewer valve near the channel closed.
- Jul 2024Metrowater reports to the NGT; Madipakkam work due by 31 Jan 2025.