Drains & sewage2022First reported by National Green Tribunal (Southern Zone)

Metrowater tells tribunal Madipakkam homes by Chitheri lake have no sewers

In March 2022, Metrowater told the National Green Tribunal that streets on the Puzhuthivakkam side of Chitheri lake had sewers, but the Madipakkam side had none. It said Rs 256.90 crore had been approved for Madipakkam's sewerage scheme.

Case
O.A. No. 135 of 2020 (SZ), National Green Tribunal
Agency
Chennai Metrowater (CMWSSB)
Scheme
Madipakkam underground sewerage scheme
Approved cost
Rs 256.90 crore (G.O.(Ms) No. 23, 31 Jan 2022)
Project period
30 months after award
Madipakkam homes by the lake
109, in 8 streets, all on septic tanks

What the report says

In July 2020, the Tamil paper Dinamalar reported that sewage was flowing like a river into Puzhuthivakkam Chitheri lake. The National Green Tribunal (NGT), a special court for environment cases, took up the matter on its own.

In March 2022, Metrowater's Superintending Engineer (South) filed a sworn report. It said the lake lies in survey number 67 of Madipakkam revenue village and is surrounded by 19 streets. Eleven of these are on the Puzhuthivakkam side (division 169) and eight are on the Madipakkam side (division 188).

Puzhuthivakkam already had sewers. Of 836 homes on its 11 streets, 824 had taken a sewer connection under the Illanthorum Inaippu scheme, which lets owners pay the fee in instalments. Notices were served on the other 12.

The Madipakkam side had no underground drainage at all. Its 109 homes, on streets such as Lakshmi Street, Raja Street, Thilagar Avenue and Yesudas Street, used septic tanks. Lorries emptied the tanks and took the waste to a Metrowater pumping station.

The money

The report said the government gave administrative approval of Rs 256.90 crore for Madipakkam's underground sewerage through G.O.(Ms) No. 23, dated 31 January 2022. A GO (Government Order) is the official order that approves a scheme and its cost. Only one bid came in for the work, on 10 March 2022, and it was being evaluated. The work was to take 30 months after award, including house connections. Until then, Metrowater promised close watch to stop sewage entering the lake.

Why it matters for Madipakkam

Underground sewerage means closed pipes under the street that carry waste to a treatment plant. Without it, septic tanks overflow in the rain and some waste reaches lakes. Chitheri lake sits right between the two neighbourhoods.

What happened next

Metrowater later told the tribunal that the contract was awarded on 24 June 2022 and work began on 1 August 2022. It expected to finish by 31 January 2025, with 10,856 house connections. In April 2025 it listed the Madipakkam work at Rs 85.20 crore with a finish date of 31 July 2025. That report did not explain why this figure is lower than the Rs 256.90 crore approval.

Timeline

  1. 23 Jul 2020Dinamalar reports sewage flowing into Puzhuthivakkam Chitheri lake; NGT takes up the case.
  2. 15 Nov 2021NGT asks for progress on sewer connections.
  3. 31 Jan 2022Rs 256.90 crore approved for Madipakkam sewerage.
  4. 10 Mar 2022One bid received.
  5. Mar 2022Metrowater files this report.
  6. 1 Aug 2022Madipakkam sewerage work begins.
  7. Apr 2025Metrowater lists a finish date of 31 Jul 2025.

Sources

  • National Green Tribunal: CMWSSB report in O.A. No. 135 of 2020 (SZ), Puzhuthivakkam Chitheri lake, 2022-03 (greentribunal.gov.in)
  • National Green Tribunal: CMWSSB report in O.A. No. 40 of 2020 (SZ) with O.A. No. 93 of 2020 (SZ), 2024-07-08 (greentribunal.gov.in)
  • National Green Tribunal: CMWSSB report in M.A. No. 7 of 2024 in O.A. No. 55 of 2020 (SZ), 2025-04-16 (greentribunal.gov.in)

Written for Namma Madipakkam in our own words from the sources above, 26 Nov 2026. Spotted a mistake? Tell us.