Michaung floods: why new storm-water drains did not save the city
After Cyclone Michaung, DT Next asked why thousands of crores spent on storm-water drains had not stopped the floods. Madipakkam was one of five priority areas that got new drains after the 2021 monsoon.
- Spent by Corporation so far
- Rs 2,191 crore
- Allocated by state
- Rs 5,166 crore
- Drains before 2023
- 2,073 km
- New drains in 2023
- 879 km
- Priority areas after 2021
- Kolathur, Pulianthope, Perambur, Pattalam, Madipakkam
- Planning report
- V. Thiruppugazh committee, May 2022
What the report said
DT Next published an analysis on 10 December 2023, a week after Cyclone Michaung flooded Chennai. It said the Greater Chennai Corporation had spent Rs 2,191 crore on storm-water drains so far. The state had set aside Rs 5,166 crore for them. (A storm-water drain carries only rainwater, not sewage.)
The city had 2,073 km of drains before 2023. That year, 879 km of new drains were built at a cost of more than Rs 2,000 crore.
Madipakkam's place in the plan
After the 2021 north-east monsoon, a committee led by retired IAS officer V. Thiruppugazh inspected the worst-hit areas. Its report, given in May 2022, guided the drain work. Kolathur, Pulianthope, Perambur, Pattalam and Madipakkam were chosen as priority areas. Their new drains had been built and linked up only a few months before the cyclone.
Why the drains failed
Residents named several reasons. Some new drains were not connected to lakes or canals, so water flowed back into streets. Drains were not desilted, so mud blocked the flow. Contractors and civic bodies did not coordinate. And work was rushed late instead of starting right after the previous monsoon.
A senior Corporation official said the lakes and rivers were already so full that rainwater could not drain into them. Residents said the cyclone's strength should not be used as an excuse. A Pattalam activist said Metrowater workers had pumped sewage into storm-water drains.
What officials promised
The Corporation said drain work would restart after the monsoon. Metrowater said sewer lines would be desilted citywide after the monsoon, and drinking-water testing had been doubled from 300 to 600 samples. Free drinking water would be supplied by lorry where needed.
Why it matters for Madipakkam
Madipakkam got new drains as a priority, yet much of it was still under water for days after Michaung. The lesson is that drains help only if they are cleaned and joined to working outlets, such as the canals to Pallikaranai and the Okkiyam Maduvu channel.