Citizen flood audit after Michaung asks for new weir at Madipakkam lake

After a lake breach in Medavakkam during Cyclone Michaung, a citizen audit traced the flooding to missing surplus channels along a chain of lakes. It proposed a new regulator and weir at the S. Kolathur-Madipakkam lake and a 300 m drain to Kovilambakkam lake.

Audit by
Dayanand Krishnan (GIS consultant) with Medavakkam Rising
Event
Cyclone Michaung, 4 Dec 2023
People affected
About 20,000-25,000
Estimated loss
About Rs 50 crore
Proposed for Madipakkam lake
Flood regulator and surplus weir; 300 m drain to Kovilambakkam lake
Agency responsible
Water Resources Department (Lower Palar division)

See the place

📍 Madipakkam Lake

Satellite pictures can be a year or more old, so they show the place, not the problem on the day. Newspaper photos belong to the papers, so we don't copy them. Residents' own photos are the best record: send yours and we will add it, with your name if you like.

What happened

On 4 December 2023, during Cyclone Michaung, the Vadakkupattu lake (Medavakkam Periya Eri) filled up and broke through a compound wall. Water up to five feet deep rushed into nearby streets and apartments. Cars were washed away. The audit put the number of people affected at 20,000 to 25,000, and the loss at about Rs 50 crore. Over 1,000 cars were damaged.

A GIS consultant, Dayanand Krishnan, worked with the Medavakkam Rising residents' group on a citizen audit. Citizen Matters published it on 16 January 2024. (GIS means computer mapping.)

What the audit found

The lake had no surplus weir. A surplus weir is a low wall that lets extra water spill out safely into a channel when the lake is full. Without it, the water broke the bund. The surplus channels that once carried water from one lake to the next had also disappeared.

The audit blamed the state Water Resources Department (WRD), which manages the lake through its Lower Palar division, for not providing flood regulators and channels, and for poor maintenance, staffing and funding.

What it proposed

The audit listed nine works along the chain of lakes. Each lake would get a flood regulator (a gate to control outflow) and a surplus weir. Missing links would be filled with 'cut-and-cover' drains, which are covered concrete channels 4 m wide and 2 m deep.

For Madipakkam, it proposed a new regulator and surplus weir at the S. Kolathur-Madipakkam lake, a 150 m drain bringing surplus from Pallikaranai Anai Eri into it, and a 300 m drain carrying its surplus on to Kovilambakkam lake. Kovilambakkam lake would then drain through a 920 m channel to the Keelkattalai surplus channel near Eachangadu junction.

Why it matters for Madipakkam

Lakes in this area are linked. When one has no safe outlet, the overflow spreads into homes. A proper weir and drain at the S. Kolathur-Madipakkam lake would let flood water move on in a controlled way instead of spilling into nearby streets.

What happens next

The audit gave no cost or timeline, and the article did not include a response from the WRD. We could not confirm whether any of these works have been taken up.

Sources

  • Citizen Matters: Lake breach in Medavakkam: Citizen flood audit unearths a host of problems, 16 Jan 2024 (citizenmatters.in)

Written for Namma Madipakkam in our own words from the sources above, 26 Nov 2026. Spotted a mistake? Tell us.