New road on Karthikeyapuram 2nd Cross Street dug up again for Metrowater work
The Corporation relaid Karthikeyapuram Second Cross Street in Madipakkam before Metrowater had finished its pipe work, so the new road had to be cut again. Residents called it a waste of public money.
- Street
- Karthikeyapuram Second Cross Street, Madipakkam
- Road relaid by
- Greater Chennai Corporation
- Road cut by
- Chennai Metrowater (CMWSSB)
- Work
- Underground drinking-water and sewer lines
- Pipe work going on for
- About 1.5 years (Feb 2024)
- Councillor quoted
- J. Shirley Thomas, Ward 187
See the place
📍 Karthikeyapuram 2nd Cross Street
Satellite pictures can be a year or more old, so they show the place, not the problem on the day. Newspaper photos belong to the papers, so we don't copy them. Residents' own photos are the best record: send yours and we will add it, with your name if you like.
What happened
DT Next reported on 22 February 2024 that the Greater Chennai Corporation had recently relaid Karthikeyapuram Second Cross Street in Madipakkam. But Chennai Metrowater (the Chennai Metropolitan Water Supply and Sewerage Board, or CMWSSB) had not finished laying its underground pipes for drinking water and sewer connections. So the board had to cut the new road to carry on.
A resident said the board had been doing underground work in the area for about one and a half years. Before the north-east monsoon, the Corporation Commissioner had inspected the area after a complaint and asked zonal officers to relay the road at once. The new road was laid without waiting for the pipe work.
What residents said
Residents said relaying the road before the pipes were done wasted taxpayers' money, and showed that departments were not working together. They said dug-up roads turn to slush in the rains and are risky for walkers and riders. They feared that after cutting the road, Metrowater would not patch or relay it properly, and the street would stay bad for months.
What the councillor said
Ward 187 councillor J. Shirley Thomas told the paper that most of Metrowater's work was complete. Any pending work would need the road to be dug up, she said, and the road would be relaid again once the underground pipe work was finished.
Why it matters for Madipakkam
This kind of dig-relay-dig cycle happened on many Madipakkam streets during 2023 and 2024, as storm-water drains, sewer lines and water pipes were laid by different agencies. Residents' associations can ask the Corporation and Metrowater to share their work schedules, so that a road is relaid only after all the digging is done.