Piped drinking water for Madipakkam
In 2018 Madipakkam was promised piped water from the sea-water plant at Nemmeli by 2019. The pipes and tanks came, but supply was only expected from July 2024.
- Money
- Rs 67.5 crore (the Centre pays 33%, the state the rest), announced in January 2018
- Spent
- Not published
- Period
- 2018 to 2024
- Cost given in 2018
- Rs 67.5 crore
- Who pays
- Centre 33%, state the rest
- Built by
- Chennai Metrowater (CMWSSB)
- Tanks
- 50 lakh litre overhead tank, 9 lakh litre underground tank
- Water for Madipakkam
- 25 million litres a day (2024)
- Promised
- 2019; supply expected from July 2024
Money given and money spent
Given Spent (₹ crore)
What this money is
Chennai Metrowater is building a piped drinking water supply for Madipakkam. In January 2018 officials told residents' associations that the scheme would cost Rs 67.5 crore. It was described as an AMRUT project, the central government's urban water and sewer scheme that followed JNNURM. The Centre would pay 33% and the state the rest.
What was promised
The water was to come from the sea-water treatment (desalination) plant at Nemmeli. A 50 lakh litre overhead tank and a 9 lakh litre underground tank were to be built in 2018 on Corporation land near Velachery Main Road and Kaiveli. Water was promised by 2019. Nearby Ullagaram, Puzhuthivakkam and Medavakkam were to benefit too.
Even in 2018, many houses already had pipe connections but no water in them.
What happened
In October 2021 Citizen Matters found that many streets in Srinivasa Nagar and Ram Nagar still got no piped drinking water, and some homes got about an hour of supply twice a week.
In February 2023 Metrowater was joining the Madipakkam scheme to the main 1,200 mm pipeline on Velachery-Tambaram Road, opposite the National Institute of Wind Energy, and warned of supply cuts.
In June 2024 Metrowater was running its last trials. Madipakkam was to get 25 million litres a day, with supply from early July 2024.
In July 2024 the ward 188 councillor said pipe work was finished in places such as Ram Nagar, but water had not yet reached homes. In Madipakkam, workers digging storm drains had cut the new water pipes because they did not know what they were, and Metrowater had to redo the connections. In August 2024 the ward 186 councillor said most houses in his ward now had drinking water connections.
In January 2026 Citizen Matters noted that Madipakkam is one of the areas that receive most of the water from the 150 million litre a day plant at Nemmeli.
Delays and problems
Supply was expected about five years after the date first given. The same streets were dug for water pipes, sewers and storm drains at different times, and pipes were damaged in the process. No final cost has been published, and we could not confirm whether the cost stayed at Rs 67.5 crore.
What is still pending (November 2026)
We found no official statement that every Madipakkam street now gets regular piped water, or how often. Metrowater's website, where project progress sheets are kept, could not be reached when we checked in November 2026.
How you can check
For a new connection or a supply problem, contact your Metrowater area office or depot. Metrowater also holds monthly open-house meetings for complaints.
File an RTI application to the Public Information Officer, Chennai Metrowater (CMWSSB). Ask for: the sanctioned and final cost of the Madipakkam water supply scheme and how much came from AMRUT; the date supply began; the list of streets with working connections; the number of connections given; and the supply timings for your street.
An RTI application costs Rs 10 in Tamil Nadu. You can pay in cash, by postal order, court fee stamp or demand draft. Copies cost Rs 2 a page. Looking at the files in the office is free for the first hour, then Rs 5 an hour. The office should reply within 30 days. If it does not, or the reply is poor, you can appeal to a senior officer in the same office, and after that to the Tamil Nadu State Information Commission.
Timeline
- 17 Jan 2018Rs 67.5 crore scheme announced; water promised by 2019
- Feb 2023Madipakkam scheme being joined to the main pipe on Velachery-Tambaram Road
- Jun 2024Final trials; 25 million litres a day expected from early July 2024
- Jul 2024Ward 188: some pipes finished but no water yet; pipes cut during drain work
- Aug 2024Ward 186: most houses now have water connections