The German-funded storm drains in the Kovalam basin
Madipakkam's new rainwater drains are part of a large project paid for partly by a loan from the German development bank KfW. It was planned in 2014 and work began only in 2022. It is still not finished.
- Money
- The loan agreement was signed on 4 March 2020, reported as Rs 1,700 to 1,714 crore. In May 2022, nine packages were estimated at Rs 447.03 crore. Work orders of Rs 150.45 crore went out for the first three, which cover Madipakkam and Ram Nagar. Earlier reports gave Rs 1,300 crore.
- Spent
- Not published. In February 2026 GCC said 62 of 124 km (about 50%) was done, and the rest was expected by July 2026.
- Period
- 2014 to 2026
- Loan agreement
- 4 March 2020, reported as Rs 1,700 to 1,714 crore
- Madipakkam is in
- Components M1 and M2
- First three packages
- 39.8 km of drains on 234 streets
- Outfalls
- 15, into the Pallikaranai marsh
- Progress (Sept 2026)
- 272.8 of 310 km built, 37.2 km left
- Due
- February 2027
Money given and money spent
Given Spent (₹ crore)
What this money is
The Kovalam basin is the low land south of Velachery that drains into the Pallikaranai marsh and then to the sea. The Greater Chennai Corporation is building a network of storm water drains here. These drains carry rainwater only, not sewage.
Most of the money is a loan from KfW, the German government's development bank. The state government and the Corporation pay the rest. The Corporation builds the drains, and their upkeep afterwards is to be paid from the state budget.
The basin was split into three parts. M1 and M2 cover Madipakkam, Adambakkam, Pallikaranai, Ram Nagar and nearby areas. M3 covers the coastal areas along East Coast Road.
How much
The agreement with KfW was signed on 4 March 2020. DT Next reported it as Rs 1,700 crore, and later as Rs 1,714 crore.
A Corporation report from April 2022 gives the split for M1 and M2. KfW would pay Rs 979.72 crore, and the state government and the Corporation Rs 463.90 crore. In May 2022 the Corporation was cleared to tender nine packages costing Rs 447.03 crore, and it had already given work orders for the first three, worth Rs 150.45 crore.
In July 2026 DT Next described the whole project, covering the Alandur, Perungudi and Sholinganallur zones, as a Rs 1,357.60 crore project. Reports use different totals, and no spending figure has been published.
What was promised for Madipakkam
The first three 'fast track' packages, called M12, M19 and M24, are in Zones 12 and 14. Together they cover 39.8 km of drains on 234 streets. About 27.3 km are new drains and 12.5 km are rebuilt old drains. They also include 79 rainwater harvesting pits, 17 sluice gates, 134 screens and 15 outfalls that let the water out into the Pallikaranai marsh.
In May 2022 DT Next said these packages would build new drains on 139 streets in Srinivasa Nagar, Sadasivam Nagar, Nanganallur, Madipakkam, Ram Nagar and Nehru Colony, and repair old drains on 95 more streets. In March 2023 wards 186, 187 and 188 were among the Perungudi zone wards listed for new drains, and the work was to take 24 months. In August 2023 two more packages for streets in Zone 14, numbers 9 and 10, were given to Kumar Builders (Rs 64.5 crore) and CMK Projects (Rs 56.8 crore). In March 2025 DT Next said Rs 650 crore of KfW money was funding drain building in Zones 14 and 15. A street-by-street list for Madipakkam has not been published.
What has been built
In August 2024 the ward 186 councillor said Rs 130 crore of storm drain work in Ram Nagar was about 75% done. In February 2026 the Corporation said 62 of the basin's 124 km were finished, with the rest due by July. By July 2026 it said 262.52 of 310.5 km were done, with completion due by February 2027. At the end of September 2026, 272.8 of 310 km were built and 37.2 km were left. The reports count different lengths, and none gives a figure for Madipakkam alone.
Delays and problems
The first plan was ready in 2014 and a feasibility study in 2019, but building did not start until 2022. Residents of the coastal area went to the National Green Tribunal, which stopped the work, and the coastal zone authority issued a stop-work notice for lack of clearance. KfW froze the money for a while in 2021, and the plan had to be redrawn.
In 2022 residents found that several Srinivasa Nagar streets, including Vivekananda, Kavimani, Balaji, Nakeeran, Padmavathi and Vallal Kathir Streets, were left out of the tender drawings. Officials blamed an old map.
In 2024 Madipakkam and Ram Nagar roads were dug up for drains, sewers and water pipes at once, and drain workers cut new water pipes by mistake.
What is still pending (November 2026)
The project is not finished; the latest date given is February 2027. No list of finished streets, no final cost and no spending figure for Madipakkam has been published. Whether the new drains actually stop flooding will only be clear after a full monsoon.
How you can check
The project's plan promised a grievance committee in each zone, chaired by the zonal officer, with residents' associations as members. Ask the Zone 14 office whether this committee meets, and take drain complaints to it.
File an RTI application with the Public Information Officer at the Zone 14 (Perungudi) office, No. 6/64 Puzhuthivakkam Main Road, Chennai 600091. Phone 9445190014 or 9445190214. Email [email protected]. Ask for: the list of streets in wards 186, 187 and 188 covered by the Kovalam basin packages; the drawing for your street; the contract value and contractor of each package; the amount paid so far; and the expected completion date. Ask also where your street's drain lets out its water.
An RTI application costs Rs 10 in Tamil Nadu. You can pay in cash, by postal order, court fee stamp or demand draft. Copies cost Rs 2 a page. Looking at the files in the office is free for the first hour, then Rs 5 an hour. The office should reply within 30 days. If it does not, or the reply is poor, you can appeal to a senior officer in the same office, and after that to the Tamil Nadu State Information Commission.
Pictures

Timeline
- 2014Detailed project report for the Kovalam basin drains prepared
- 2019Feasibility study for M1 and M2 finished
- 4 Mar 2020Corporation signs the loan agreement with KfW
- Sep 2021Coastal works stopped; KfW freezes funds; plan to be redrawn
- Apr 2022Environmental report for the first three packages (M12, M19, M24)
- May 2022Work orders worth Rs 150.45 crore issued; Madipakkam streets included
- May 2022Several Srinivasa Nagar streets found missing from tender drawings
- Aug 2023Packages 9 and 10 for Zone 14 streets awarded, Rs 121.3 crore together
- Aug 2024Rs 130 crore of drains in Ram Nagar about 75% done
- Feb 2026Corporation says 62 of 124 km done
- Jul 2026Corporation says 262.52 of 310.5 km done; due February 2027
- Sep 2026272.8 of 310 km built; 37.2 km left