Madipakkam's underground sewerage scheme

Madipakkam waited more than ten years for sewer pipes. The scheme was approved in 2022 and was due to finish by July 2025, but no report says it is complete.

Money
Outline cost Rs 160 crore. The DPR consultancy was awarded on 24 Oct 2016 for Rs 1.49 crore.
Spent
Not published
Period
2016 to 2024+
Built by
Chennai Metrowater (CMWSSB)
Approved cost
Rs 256.90 crore, G.O.(Ms) No. 23, 31 Jan 2022
Planned sewers
98.84 km, 6 pumping stations
House connections planned
9,750
People served (2019 plan)
48,710, over 3.4 sq km
Due date given (April 2025)
31 July 2025

Money given and money spent

Given Spent (₹ crore)

2016 outline estimate160 / –
Jan 2022 government approval256.9 / –
Apr 2025 estimate given to tribunal85.2 / –

What this money is

Homes in Madipakkam without sewers use septic tanks, which are emptied by sewage lorries. The underground sewerage scheme lays pipes under the streets to carry waste water from every house to pumping stations, and from there to a sewage treatment plant. Chennai Metrowater, officially the Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB), plans and builds it. The state government approves the cost.

How much

In October 2016 Metrowater hired a consultant for Rs 1.49 crore to prepare the detailed plan for Madipakkam and 13 other added areas. At that time the scheme was roughly costed at Rs 160 crore.

On 31 January 2022 the state's Municipal Administration and Water Supply department gave administrative approval for Rs 256.90 crore, in Government Order G.O.(Ms) No. 23. Only one bid came in, on 10 March 2022.

In April 2025, in a report to the National Green Tribunal, Metrowater listed the Madipakkam scheme with an estimated cost of Rs 85.20 crore and a completion date of 31 July 2025. The report does not explain why this is lower than the 2022 approval. How much has been spent has not been published.

What was promised

The 2019 plan was for 98.84 km of sewer pipes, 8.8 km of pumping mains and 9,750 house connections, serving 48,710 people over 3.4 sq km. It was designed to last 30 years. Six pumping stations were planned: at the Dumping Yard, Rajalakshmi Nagar, Mylai Balaji Nagar and Senthil Nagar, a roadside station on Madipakkam Lake View Road, and one at Karpagambal Nagar. Once the contract was given, the work was to take 30 months.

Delays

The scheme was first planned around 2011. In July 2019, hearing a public interest case filed by a Madipakkam resident, the Madras High Court asked Metrowater for a report. Metrowater then said building would start by July 2020. It did not.

In March 2022 Metrowater told the National Green Tribunal, in a case about sewage reaching the Puzhuthivakkam Chitteri lake, that Madipakkam still had no sewer system. It listed eight streets near the lake with 109 homes still on septic tanks: Lakshmi Street, Raja Street, Thilagar Avenue and its 1st, 8th and 9th Streets and Cross Street, and Yesudas Street.

What has been built

Work was under way by 2023. In June 2023 the Corporation said sewer pipes were being laid on 124 of the 457 roads in wards 187 and 188, and 40 roads were finished. By July 2023 the Corporation had allowed 153 roads to be dug for sewers. Metrowater had handed back 66 of them after giving house connections. A base layer of crushed stone had been laid on 30 of these, and 24 were being concreted or tarred.

In August 2024 the ward 186 councillor said most houses in his ward now had sewer and water connections.

Problems along the way

Roads have been dug again and again. In February 2024 a newly relaid road on Karthikeyapuram Second Cross Street was cut open again because the pipe work under it was not finished. In 2024 the ward 188 councillor said sewer work dug up the middle of roads and disturbed water supply and streetlights.

What is still pending (November 2026)

The last date given, 31 July 2025, has passed, and no completion report has been published. It is not known how many of the 9,750 house connections have been given, which streets are still not connected, or whether all six pumping stations are working. In September 2025 residents said the lack of sewer connections in some areas was still the main reason sewage reaches Madipakkam Lake.

How you can check

For a connection, contact your local Metrowater depot. Metrowater's tribunal report refers to the Madipakkam area as Depot 188 in its Area 14. In nearby Puzhuthivakkam, Metrowater has let households pay the sewer connection charge at once or in instalments; ask whether the same applies to your street.

File an RTI application to the Public Information Officer, Chennai Metrowater (CMWSSB). Ask for: a copy of G.O.(Ms) No. 23 of 31 January 2022; the contract value, contractor and start date; the planned and revised completion dates; the length of sewer laid so far; the number of house connections given; the list of streets not yet covered; and the status of each pumping station.

An RTI application costs Rs 10 in Tamil Nadu. You can pay in cash, by postal order, court fee stamp or demand draft. Copies cost Rs 2 a page. Looking at the files in the office is free for the first hour, then Rs 5 an hour. The office should reply within 30 days. If it does not, or the reply is poor, you can appeal to a senior officer in the same office, and after that to the Tamil Nadu State Information Commission.

Timeline

  1. About 2011Sewer scheme for Madipakkam first planned
  2. 24 Oct 2016Consultant hired for Rs 1.49 crore to prepare the plan
  3. Jul 2019In a public interest case, the High Court asks Metrowater for a report; building promised by July 2020
  4. 31 Jan 2022Government approves Rs 256.90 crore (G.O.(Ms) No. 23)
  5. 10 Mar 2022One bid received for the work
  6. Jun 2023Sewer pipes being laid on 124 roads in wards 187 and 188
  7. Jul 202366 of 153 dug roads handed back after house connections
  8. Feb 2024Relaid road on Karthikeyapuram 2nd Cross Street cut again
  9. Aug 2024Ward 186 councillor says most houses now connected
  10. 16 Apr 2025Metrowater tells the Green Tribunal the scheme costs Rs 85.20 crore and will finish by 31 July 2025

Sources

  • Deccan Chronicle, 4 Jul 2019: Working on final report, CMWSSB (deccanchronicle.com)
  • News Today, 22 Jul 2019: Construction of Madipakkam underground sewage network to begin (newstodaynet.com)
  • Citizen Matters, 5 Jul 2024: Ward 188 councillor (citizenmatters.in)
  • Deccan Chronicle: Working on final report, CMWSSB, 2019-07-04 (deccanchronicle.com)
  • News Today: Construction of Madipakkam underground sewage network to begin, 2019-07-22 (newstodaynet.com)
  • NGT Southern Zone, O.A. No. 135 of 2020: Report filed by CMWSSB (Puzhuthivakkam Chitteri lake sewage), 2022-03 (greentribunal.gov.in)
  • NGT Southern Zone, M.A. No. 7 of 2024 in O.A. No. 55 of 2020: Report filed by CMWSSB (UGSS estimate and completion dates), 2025-04-16 (greentribunal.gov.in)
  • DT Next: GCC Commissioner inspects road restoration works in Madipakkam, 2023-06-22 (dtnext.in)
  • DT Next: CS Shiv Das Meena inspects works around Chennai, 2023-07-09 (dtnext.in)
  • DT Next: Citizen connect: Re-laid road cut for CMWSSB's incomplete work in Madipakkam, 2024-02-22 (dtnext.in)
  • Citizen Matters: Councillor Talk, Ward 187 (Madipakkam), 2023-11-01 (citizenmatters.in)
  • Citizen Matters: Councillor Talk, Ward 188, 2024-07-05 (citizenmatters.in)
  • Citizen Matters: Councillor Talk, Ward 186, 2024-08-05 (citizenmatters.in)
  • Citizen Matters: From neglect to nurture: How a proactive community revived Chennai's Madipakkam Lake, 2025-09-24 (citizenmatters.in)
  • Tamil Nadu Information Commission: Fees to be paid under RTI in Tamil Nadu (tnsic.gov.in)

Written for Namma Madipakkam in our own words, 27 Nov 2026. Figures are as published; "not published" means we could not find it. Spotted a mistake? Tell us.