Where the money goes

What the auditor found in Metrowater's sewer spending

A national audit of Chennai's sewage system for 2014 to 2019 found that Metrowater spent only 40% of its planned project budget, and that most of the areas added to the city, like Madipakkam, still had no sewers.

Money
2014-19 capital budget; Rs 1,610.68 crore received from funding sources
Spent
Only 40% of the planned capital spending happened: Rs 1,244.41 crore, or 77% of the money received.
Period
2014-15 to 2018-19
Planned for projects, 2014-19
Rs 3,105.20 crore
Money received
Rs 1,610.68 crore
Spent
Rs 1,244.41 crore (40% of plan)
Added areas with sewers (2019)
11 of 42
Raw sewage into drains and rivers
242.73 million litres a day
Grant to be lost
Rs 18.49 crore

Money given and money spent

Given Spent (₹ crore)

2014-15655.94 / 106.7
2015-16925.93 / 240.96
2016-17718.27 / 233.05
2017-18427.14 / 244.54
2018-19377.92 / 419.16

What this audit is

The Comptroller and Auditor General of India (CAG) checks how governments spend public money. Its audit report on Tamil Nadu for the year ending March 2019 has a full chapter on sewage in the Chennai area, covering 2014 to 2019. It looked at Chennai Metrowater (CMWSSB), which builds and runs sewers. The state government gave its replies in April 2020.

The chart shows Metrowater's budget for projects each year against what it actually spent.

How much was planned and spent

Over the five years, Metrowater budgeted Rs 3,105.20 crore for projects. It received Rs 1,610.68 crore from the state, the Centre and loans, and spent Rs 1,244.41 crore. That is only 40% of the plan, and 77% of the money it actually had. In 2014-15 it spent just 16% of its project budget. The audit said every project it examined was delayed.

What it found about areas like Madipakkam

Madipakkam was one of the 42 local areas added to the Corporation. The audit found that by November 2019 only 11 of these 42 areas had underground sewers. Work was going on in 14 more, costing Rs 1,252.05 crore. Plans were approved or being prepared for 12 others, and five had no proposal at all. The part of the report we read does not name Madipakkam, but in 2019 Madipakkam's own plan was still being written.

Only 52% of the sewage made in the Chennai area was collected by sewers in March 2019. The rest was not collected. Metrowater itself estimated that 242.73 million litres of raw sewage a day entered storm drains and flowed into the Adyar, the Cooum and the Buckingham Canal. The law that set up Metrowater forbids letting sewage into storm drains.

Nearby projects that went wrong

The sewer scheme for Perungudi was due in November 2012, but had made no progress by May 2020. The state blamed sandy soil, late handing over of land and the moving of cables and pipes; the auditor blamed poor planning.

Pallikaranai's scheme was due in February 2013. Work stalled after July 2017, the contract was ended after a court case, and fresh tenders were called in January 2020, a delay of over seven years.

A 2009 plan to give sewers to eight town panchayats, including Pallikaranai, Perungudi, Madambakkam and Chitlapakkam, was mostly dropped. Grants of Rs 38.78 crore from the Centre and the state were returned.

Keelkattalai's pumping station sends sewage to the Perungudi treatment plant. For 199 days between November 2017 and June 2018, a burst pipe meant an estimated 2,398 million litres of sewage never reached the plant and went into water bodies untreated.

The cost of delay

Delays raised the cost of three sewer projects by Rs 82.91 crore. Six delayed projects had been funded under the central JNNURM scheme. That scheme has ended, so Rs 18.49 crore of central grant would not be received, and the state would have to pay it.

What is still pending (November 2026)

The audit covers 2014 to 2019. Madipakkam's own sewer scheme was approved in 2022 and is still being finished. We found no published report on what action Metrowater took on each audit finding.

How you can check or push

The full chapter is free on the CAG website. File an RTI application to the Public Information Officer, Chennai Metrowater (CMWSSB). Ask for: the action taken on the CAG findings about sewerage in added areas; the current status of the Perungudi and Pallikaranai sewer schemes; and the number of known sewage outlets into storm drains in Zone 14 and how many have been closed.

An RTI application costs Rs 10 in Tamil Nadu. You can pay in cash, by postal order, court fee stamp or demand draft. Copies cost Rs 2 a page. Looking at the files in the office is free for the first hour, then Rs 5 an hour. The office should reply within 30 days. If it does not, or the reply is poor, you can appeal to a senior officer in the same office, and after that to the Tamil Nadu State Information Commission.

Timeline

  1. Nov 2012Perungudi sewer scheme due; no progress by May 2020
  2. Feb 2013Pallikaranai sewer scheme due; delayed over seven years
  3. 2014-15 to 2018-19Metrowater spends Rs 1,244.41 crore of Rs 3,105.20 crore planned
  4. Nov 2017 to Jun 2018Burst pipe: Keelkattalai sewage fails to reach Perungudi plant for 199 days
  5. Nov 2019Only 11 of 42 added areas have sewers
  6. Apr 2020State government replies to the audit

Sources

  • CAG Audit Report (General and Social Sector) Tamil Nadu 2018-19, Chapter II (cag.gov.in)
  • CAG Audit Report (General and Social Sector), Tamil Nadu, year ended March 2019, Chapter II: Sewerage in Chennai Metropolitan Area, 2020 (cag.gov.in)
  • Deccan Chronicle: Working on final report, CMWSSB, 2019-07-04 (deccanchronicle.com)
  • NGT Southern Zone, O.A. No. 135 of 2020: Report filed by CMWSSB (Puzhuthivakkam Chitteri lake sewage), 2022-03 (greentribunal.gov.in)
  • Tamil Nadu Information Commission: Fees to be paid under RTI in Tamil Nadu (tnsic.gov.in)

Written for Namma Madipakkam in our own words, 27 Nov 2026. Figures are as published; "not published" means we could not find it. Spotted a mistake? Tell us.