State flood works after the Thiruppugazh committee

After the 2021 floods, a state expert committee drew up a plan to protect Chennai. Several of the works it led to are on the channels that drain Madipakkam into the Pallikaranai marsh. The committee's full report has never been made public.

Money
In May 2022, Rs 184.22 crore was approved for Chennai and Chengalpattu. This included Rs 96.5 crore for channels into the Pallikaranai marsh, Rs 68.82 crore for a missing main-drain link, Rs 13.9 crore for a link from the Adambakkam tank to Veerangal Odai, and Rs 5 crore for Okkiyam Maduvu. Another Rs 27 crore job on Okkiyam Maduvu began in June 2025, the first part of a Rs 338 crore WRD programme.
Spent
Not published. In October 2024 the Chief Minister said 70-75% of the committee's works were done.
Period
2022 to 2026
Committee
Flood risk advisory committee, chaired by V. Thiruppugazh (retired IAS)
Final report
14 March 2023, 161 recommendations, not published
First works
Rs 184.22 crore, May 2022
Built by
Water Resources Department
Later programme
Rs 338 crore, launched June 2025
Spending figures
Not published

Money given and money spent

Given Spent (₹ crore)

May 2022: channels to Pallikaranai marsh96.5 / –
May 2022: missing link drain68.82 / –
May 2022: Adambakkam to Veerangal Odai13.9 / –
May 2022: Okkiyam Maduvu5 / –
Jun 2025: Okkiyam Maduvu, phase 127 / –

What this money is

After heavy flooding in 2021, the state government set up an advisory committee on flood risk in the Chennai area, headed by V. Thiruppugazh, a retired IAS officer. It gave an interim report in May 2022 and a final report on 14 March 2023, with 161 recommendations. The works it recommended are paid for by the state and built mostly by the Water Resources Department (WRD), which looks after lakes, rivers and large channels.

This matters for Madipakkam because the area's rainwater runs through channels into the Pallikaranai marsh, and from there through Okkiyam Maduvu and the Buckingham Canal to the sea. When that route is blocked, water backs up into Madipakkam and Ram Nagar.

How much, and what was promised

In May 2022 the government sanctioned Rs 184.22 crore for four works in Chennai and Chengalpattu districts, to be finished before that year's monsoon:

Rs 96.5 crore for flood channels from the Ottiyambakkam channel and Madurappakkam drain to the Pallikaranai marsh, covering Semmencherry and Perumbakkam.

Rs 68.82 crore for a covered main drain to close the missing link between the Ottiyambakkam and Arasankalani tanks, and the link to the marsh.

Rs 13.9 crore to modernise the link channel from the Adambakkam tank to Veerangal Odai, the channel that takes surplus water from the Adambakkam lake towards the Pallikaranai marsh.

Rs 5 crore to dredge and regrade Okkiyam Maduvu up to the Buckingham Canal near KCG College.

In June 2025 the WRD started a Rs 338 crore flood programme for Chennai, Tiruvallur and Kancheepuram, with 12 works. The first was a Rs 27 crore job on Okkiyam Maduvu, launched with the Sholinganallur MLA present.

What was built

In October 2024 the then Chief Minister said 70 to 75% of the committee's works were done. He told officials to speed up desilting of the Veerangal canal.

In October 2026 Deccan Chronicle reported that the Okkiyam Maduvu work was nearing completion. The 2.65 km channel links the marsh to the Buckingham Canal. An opening in the Sholinganallur zone is being widened from 10 metres to 98 metres, more than 2 lakh cubic metres of silt removed, and a 520 metre flood wall built. The paper said it should stop the backflow that floods Madipakkam and Ram Nagar.

Closer to home, in September 2026 the Chief Secretary inspected channel work at Mylai Balaji Nagar. A 235 metre stretch, 13 metres wide, was being improved for Rs 6.48 crore, and a 207 metre stretch for Rs 8.68 crore. The channel carries rain water along the Velachery-Medavakkam road to the marsh, draining Ram Nagar (South), Kubera Nagar and Sadasivam Nagar. The reports did not say which department was building it or which fund paid. On the same visit he checked a Rs 73 crore Highways Department drain at Thoraipakkam that takes water from the marsh to the Buckingham Canal.

Delays and problems

The final report has not been published. In August 2026 PMK leader Anbumani Ramadoss asked the new government to table it, saying it had stayed hidden for 41 months. The previous government had said 101 of the 161 recommendations were being carried out, but gave no details.

This is an old problem. In 2017 the national auditor (CAG) found that the WRD had not kept Veerangal Odai clear, which led to flooding in Adambakkam during the 2015 floods. During Cyclone Michaung in 2023, ward 188 residents saw water flow backwards from the marsh into their homes.

What is still pending (November 2026)

No spending figures have been published for any of these works. Okkiyam Maduvu was nearing completion in October 2026. The full list of 161 recommendations, and which of them concern Madipakkam, is still not public.

How you can check or push

File an RTI application to the Public Information Officer, Water Resources Department, Chennai. Ask for: the status, cost and amount spent on each of the four works sanctioned in May 2022; the progress of the Okkiyam Maduvu work; and the desilting done on Veerangal Odai and the channels from Madipakkam to the marsh in 2025 and 2026.

You can also ask for a copy of the Thiruppugazh committee's final report under RTI. If it is refused, you can appeal.

An RTI application costs Rs 10 in Tamil Nadu. You can pay in cash, by postal order, court fee stamp or demand draft. Copies cost Rs 2 a page. Looking at the files in the office is free for the first hour, then Rs 5 an hour. The office should reply within 30 days. If it does not, or the reply is poor, you can appeal to a senior officer in the same office, and after that to the Tamil Nadu State Information Commission.

Pictures

Okkiyam Maduvu in flood on 4 December 2015. This channel takes water from the Pallikaranai marsh to the Buckingham Canal, and is now being widened.
Okkiyam Maduvu in flood on 4 December 2015. This channel takes water from the Pallikaranai marsh to the Buckingham Canal, and is now being widened.Photo: Phani.raghavendra.sanduri · CC BY-SA 4.0

Timeline

  1. 2015CAG later finds Veerangal Odai was not kept clear, flooding Adambakkam
  2. 2021Flood risk advisory committee set up under V. Thiruppugazh
  3. May 2022Interim report; Rs 184.22 crore sanctioned for four works
  4. 14 Mar 2023Final report with 161 recommendations handed in
  5. Oct 2024Chief Minister says 70-75% of works done
  6. 30 Jun 2025Rs 338 crore WRD programme begins with Rs 27 crore Okkiyam Maduvu work
  7. 23 Aug 2026Opposition leader asks for the report to be tabled
  8. Sep 2026Chief Secretary inspects Mylai Balaji Nagar channel works
  9. 17 Oct 2026Okkiyam Maduvu work reported nearing completion

Sources

  • DT Next, 20 May 2022: Tamil Nadu allots Rs 184 crore for flood works (dtnext.in)
  • DT Next, 17 Oct 2024: Once these are implemented, city's flooding woes will be solved (dtnext.in)
  • DT Next, 23 Aug 2026: Table Thirupugazh report, says Anbumani Ramadoss (dtnext.in)
  • Adyar Times, 1 Jul 2025: Rs 338 crore flood control project (adyartimes.in)
  • DT Next: Tamil Nadu allots Rs 184 crore for flood works in Chennai, Chengalpattu, 2022-05-20 (dtnext.in)
  • DT Next: Chennai rains: Once these are implemented, city's flooding woes will be permanently solved, 2024-10-17 (dtnext.in)
  • DT Next: Table Thirupugazh report on preventing flooding in Chennai, says Anbumani Ramadoss, 2026-08-23 (dtnext.in)
  • Adyar Times: Minister Duraimurugan launches major Rs 338 crore flood control project in Chennai region, 2025-07-01 (adyartimes.in)
  • Deccan Chronicle: Okkiyam Maduvu project to be major gamechanger for south Chennai, 2026-10-17 (deccanchronicle.com)
  • DT Next: Chief Secretary inspects drainage and canal works in south Chennai ahead of northeast monsoon, 2026-09-06 (dtnext.in)
  • Indian Masterminds: Chennai monsoon preparedness, Chief Secretary reviews stormwater drain works, 2026-09-06 (indianmasterminds.com)
  • CAG Report No. 4 of 2017 (Tamil Nadu), Chapter 5: Drainage system in Chennai Metropolitan Area, 2017 (cag.gov.in)
  • Citizen Matters: Councillor Talk, Ward 188, 2024-07-05 (citizenmatters.in)
  • Tamil Nadu Information Commission: Fees to be paid under RTI in Tamil Nadu (tnsic.gov.in)

Written for Namma Madipakkam in our own words, 27 Nov 2026. Figures are as published; "not published" means we could not find it. Spotted a mistake? Tell us.