Before the 2015 floods: the auditor's report on drains

The national auditor studied why Chennai flooded in December 2015. It found that Madipakkam's zone had drains on only 12% of its roads, that drains were built too small, and that cleaning was skipped or done late.

Money
Annual desilting works for waterways in the metro area
Spent
None of the desilting works approved for 2014 and 2015 was finished before the monsoon.
Period
April 2011 to March 2016
Audit
CAG Report No. 4 of 2017, covering 2011 to 2016
Corporation spending on drains
Rs 855.80 crore in five years, 4-8% of its spending
Perungudi zone roads with drains (2016)
55.94 of 455.47 km, 12%
Perungudi zone drains not cleaned
All 898 drained streets, 2015-16
Rainfall used for design
31.39 mm an hour, instead of about 49
December 2015 floods
289 deaths, 23.25 lakh houses flooded

Money given and money spent

Given Spent (₹ crore)

2011-12– / 78.31
2012-13– / 163.89
2013-14– / 237.03
2014-15– / 206.21
2015-16– / 170.36

What this audit is

After the December 2015 floods, which killed 289 people and flooded 23.25 lakh houses, the Comptroller and Auditor General (CAG) studied flood management in Chennai and its suburbs. The audit was done between June and November 2016 and covers April 2011 to March 2016. It was published as Report No. 4 of 2017.

Madipakkam had joined the Corporation in 2011 as part of the new Perungudi zone, one of the five zones the auditor checked in detail.

How much was spent on drains

The Corporation spent Rs 855.80 crore on storm drains over the five years from 2011-12 to 2015-16, as the chart shows. That was only 4 to 8% of its total spending each year. The auditor called this too little, given how many streets had no drains.

What it found for Madipakkam's zone

A 2006 city plan set a target of drains on 40% of Perungudi zone's roads by 2011 and 60% by 2016. By August 2016, only 55.94 km of the zone's 455.47 km of roads had drains: 12%. In Perungudi zone, 1,901 streets had no storm drain at all.

Cleaning was worse. Under the Corporation's own disaster plan, drains were to be cleaned before each monsoon. In 2015-16, the year of the great flood, the drains in all 898 Perungudi zone streets that had them were not cleaned.

Drains built too small

Drains must be sized for heavy rain. Two expert studies had found that Chennai's drains should be designed for about 49 mm of rain an hour. The Corporation used a lower figure, 31.39 mm an hour, and built 345 km of drains for Rs 610.55 crore between 2011 and 2014 under the central JNNURM scheme. The auditor said these drains were too small and helped cause the 2015 floods.

The Corporation also had no master plan for storm drains. In November 2014 it found 52 places where drains were not connected to anything. In October 2016 there were 233 illegal sewer lines joined to storm drains, which made them hard to clean.

Desilting money came late

The Water Resources Department proposes desilting and clearing of waterways before every monsoon. In 2014 and 2015 the state approved this money only around the time the monsoon began: on 13 October 2014 and 29 October 2015. As a result, 84 works were started after the rains had begun, and in those two years none of the approved works was finished before the monsoon. About Rs 3.6 crore a year was spent on these works from 2011 to 2015 in the three river basin divisions the auditor checked.

The auditor also found that Veerangal Odai, the channel that drains the Adambakkam lake towards the Pallikaranai marsh, had not been kept clear, which led to flooding in Adambakkam. Eight JNNURM channel projects in the Chennai area were stuck because of encroachments.

What changed, and what is still pending (November 2026)

The auditor asked for a storm drain master plan for each watershed, the correct rainfall figure in design, and yearly maintenance. Since then, new drains have been built in Madipakkam under the German-funded Kovalam basin project, which was due to be finished in February 2027. We found no published report on how the Corporation acted on each recommendation.

How you can check or push

The full report is free on the CAG website. Ask the Zone 14 office, under RTI, for the design rainfall figure used for the new drains in your street, the date the drains in your street were last cleaned, and the pre-monsoon desilting plan for this year. Write to the Public Information Officer at the Zone 14 (Perungudi) office, No. 6/64 Puzhuthivakkam Main Road, Chennai 600091. Phone 9445190014 or 9445190214. Email [email protected].

An RTI application costs Rs 10 in Tamil Nadu. You can pay in cash, by postal order, court fee stamp or demand draft. Copies cost Rs 2 a page. Looking at the files in the office is free for the first hour, then Rs 5 an hour. The office should reply within 30 days. If it does not, or the reply is poor, you can appeal to a senior officer in the same office, and after that to the Tamil Nadu State Information Commission.

Timeline

  1. 2011Madipakkam joins the Corporation in the new Perungudi zone
  2. 2011-14345 km of drains built for Rs 610.55 crore, designed for too little rain
  3. 13 Oct 2014Desilting money approved only as the monsoon begins
  4. 29 Oct 2015Desilting money approved after the monsoon begins
  5. Dec 2015Floods kill 289 people in Chennai and its suburbs
  6. Aug 2016Only 12% of Perungudi zone roads have drains
  7. 2017CAG Report No. 4 of 2017 published

Sources

  • CAG Report No. 4 of 2017: Executive Summary (cag.gov.in)
  • CAG Report No. 4 of 2017: Executive summary, Performance audit of flood management and response in Chennai, 2017 (cag.gov.in)
  • CAG Report No. 4 of 2017 (Tamil Nadu), Chapter 5: Drainage system in Chennai Metropolitan Area, 2017 (cag.gov.in)
  • Greater Chennai Corporation: Who's Who (zone office contacts) (chennaicorporation.gov.in)
  • Tamil Nadu Information Commission: Fees to be paid under RTI in Tamil Nadu (tnsic.gov.in)

Written for Namma Madipakkam in our own words, 27 Nov 2026. Figures are as published; "not published" means we could not find it. Spotted a mistake? Tell us.